Captain: from a prospect to production

Innovation and pioneering spirit are concepts which quickly spring to mind whichever way you consider the Captain field development. One of a new generation of heavy crudes to be produced from the North Sea, Captain's success has only been made possible by turning conventional thinking completely on its head.

At an SPE dinner meeting last month in London, Captain field development manager Shah Etebar explained how a field discovered in 1977 moved from being an unattractive prospect to the top of Texaco's North Sea portfolio by the triple drivers of new technology, a reorganisation of the project team and a fresh approach to the development strategy.

It was clear from the outset that economical extraction of the viscous (88 cp), heavy (20°API), low GOR (130 scf/bbl) crude oil from a shallow reservoir (3000 ft) in unconsolidated sand and with a large areal extent (10 km x 4 km) would present a big challenge. The lack of existing infrastructure in the vicinity of Captain's location in block 13/22a, some 80 miles north east of Aberdeen, was a further drawback.

Said Shah: "Using conventional methods we would have needed in excess of 300 wells drilled from over ten drilling centres. The low crude mobility allows for water break through during the early stages of production, thereby reducing overall oil recovery and increasing the requirement for water handling, and the stable emulsions formed necessitate site specific separation facilities. In addition, the relatively high naphthenic acid content (2.5 mg KOH/g) of the oil presented a marketing issue at the time to refiners without the appropriate process facilities in place."

It is not surprising therefore that there was a 12-year gap between the discovery of Captain and drilling of the first appraisal well. From there the project progressed more positively. Following the formation of the Captain team in 1992, a ten well appraisal programme was completed in 1993, including extended well tests, in parallel with topsides definition engineering. In December 1994 the development contract was awarded, project sanction was achieved and detailed engineering started. In January 1995, the UK government sanctioned field development and first oil is due in December this year. A second area of the field is planned to be brought on stream by the end of the century.

Peak production of 60,000 barrels a day is expected to be maintained for the first seven years of Captain's estimated 20-year life. This production rate could potentially be increased to 100,000 barrels a day. Recoverable reserves are estimated to be in excess of 300 million barrels.

So how did Texaco turn Captain around?

A Texaco North Sea UK company upstream reorganisation during 1992 implemented sweeping changes in the way projects were to be developed. Multi-discipline teams in a new "asset development" structure were charged with the task of bringing existing assets into commercial reality as quickly as possible while adding significant value to the company.

The small, hand-picked, multi-skilled Captain team was designated as a business unit with the authority and responsibility for making its own decisions. The team comprised only seven people: senior reservoir engineer, reservoir engineer, geologist, geophysicist, facilities engineer, process engineer and a prospect manager.

The first task of the Captain team was to formulate a field development strategy knowing that conventional thinking and methods would yield unsatisfactory results.

The team determined that the Captain field could be developed if 6000 ft long horizontal wells could be drilled and completed in the shallow unconsolidated reservoir. This way, the number of wells and drilling centres could be reduced significantly. A parallel appraisal and engineering programme was devised to put this strategy into action and it reduced the development cycle time by around two years.

In April 1993 a 6000 ft horizontal section well was successfully drilled and completed from the John Shaw semi-submersible rig and tested for a period of 90 days. Production rates in excess of 11,000 bopd were achieved through a purpose-built processing system and exported to an adjacent tanker. A further nine appraisal wells provided vital information to help determine the boundary of the reservoir and the quantity of oil in place.

"Although Captain was recognised as a difficult reservoir and data collection and analysis acknowledged as essential to mitigate risk, the sense of urgency in moving forward and achieving business results was always present," Shah said.

In parallel with the reservoir appraisal programme, Texaco embarked on an unconventional contractor selection process. As a basis for contractor selection and eventual production, a staged development was planned in order to minimise initial capital investment. This was because of the requirement for at least two drilling centres to develop and produce all currently proven hydrocarbons. The initial development area covers the western sector of the Captain field and will contain all processing and export facilities.

These facilities consist of a wellhead platform connected by subsea pipelines to a floating production, storage and offloading (FPSO) vessel with 550,000 barrels' capacity, from which export quality crude will be offloaded by shuttle tanker for shipment to international markets.

Seven horizontal wells have been pre-drilled through a template with a semi-submersible rig and will be tied back prior to final hook-up and commissioning of the production facilities on the FPSO. There will be five production wells, one water source well and one water injector. Full plateau production will be possible from the outset, thus improving the project economics. Electric submersible pumps are being used to optimise production.

From the beginning, the Captain team adopted an "alliance" style approach to the contract for the facilities, which was designed to align the aims of the contractor with those of Texaco. Instead of requesting bids based upon a single development scenario, Texaco invited contractors to propose schemes based simply on a functional specification.

The contracting strategy was based on the following premises:

"The three short-listed contractors were asked to undertake certain funded layout and design studies with the aim of firming up all parts of their proposals," Shah noted. The proposal submitted by ABB Lummus Global, Coflexip Stena, Astano and UiE was the one finally selected. ABB was responsible for the design, procurement and project management; Coflexip Stena for the offshore installation and hook-up; Astano in Spain for the FPSO; and UiE for the fabrication of the wellhead protection platform.

The goals of the contractors were aligned with Texaco's by the principle of shared risk and reward through a "target price" mechanism. The target price itself comprises three main elements:

All the costs were declared at the bid stage and were clarified and agreed with Texaco. When the project is completed below the target price, the joint venture partners and Texaco will share the savings and the joint venture will also keep the fixed profit amount. If the project is completed at the target price, the joint venture will retain the fixed profit element only. Should the final price exceed the target price, then the excess cost is shared on the same percentage basis between the joint venture and Texaco. This situation is limited by a fixed amount, the total of which is termed the "cap price", after which Texaco will pay 100 per cent of the costs incurred without profit accruing to the joint venture.

The value of the difference between the target and cap prices is set such that the majority of the fixed profit element is lost by the joint venture partners if they reach the cap price. There is also a risk and reward scheme for meeting the schedule completion date. Added Shah: "There is, therefore, alignment between all members of the project since all have an incentive to minimise expenditure in all areas and bring the field on stream as early as possible. This philosophy has allowed Texaco to use a very small team (never over 40) to manage the Captain project as compared to a typical large offshore development team."

Summing up, Shah reflected that despite difficult circumstances it has been possible to bring the Captain field to the brink of production through an innovative approach to field development, utilising individual excellence and expertise, sound management, dedication, openness, effective communication, team work and good cost control and financial reporting.

The experiences gained working on Captain and the lessons learned are already being applied successfully to other Texaco - and indeed industry - projects around the world.


SPE London Section : Return to home page