Over the past few years a new generation of heavy crude oils
has been produced from the North Sea, posing a number of operational
and marketing challenges to operators. At a recent SPE panel session
in London, representatives from three companies outlined how they
have overcome these challenges and, indeed, turned them into opportunities.
Gryphon was the first heavy oil field to come onto production
in the North Sea in 1993. Mike Mansell of field operator
Kerr-McGee explained that a number of things had to be done differently
to make the development economically viable and to facilitate
early production.
The field has been developed using a floating production, storage
and offloading system (FPSO) connected to a subsea wellhead cluster
located some 1.5 km away. Shuttle tankers offload the oil for
export to international markets.
The Gryphon FPSO was also the first to be moored permanently on location ñ made possible by the ship being designed and constructed to weathervane around the moored turret to maintain its heading into the prevailing weather.
The development concept called for hori-zontal wells to minimise
gas and water breakthrough and enhance long-term oil production
rates. The fewer wells required would also ultimately result in
better oil recovery.
Added Mike: The production profile is typical for heavy
oil fields, with early peak production but more water than oil
produced over the life of field.
Reservoir modelling showed the optimum position for the horizontal
section of the wells to be 45 ft below the gas/oil contact, although
Mike noted that gas production has turned out to be higher than
predicted. Later wells were therefore completed 65 ft below the
gas/oil contact.
The Gryphon development was the first in the world to use a subsea
spool tree system - the innovative design of which allows
drilling and completion operations to follow tree installation.
Mike said that the spool tree allows substantial time savings
and increased safety during well completions and workovers compared
to conventional subsea trees.
The main processing plant - which is located on a support
frame across the main deck of the ship ñ consists of a
single process train with two stages of three-phase separation,
followed by an electrostatic coalescer. Heat required for separation
is provided by a closed-loop heating medium system from waste
heat recovery units installed in the exhaust system of the two
turbine alternators. Demulsifiers are used to assist the separation
process. Furthermore, the alignment of the separators lengthways
along the ship ensures minimal roll since the ship always faces
into the weather.
Offshore loading means that pure Gryphon crude
is delivered to refineries which has turned out to be quite an
advantage, according to Mike. Before production started,
we had established a market with niche refiners
and those wishing to use heavier crudes as a blend in their crude
slates. Gryphon crude has the added advantages of a low sulphur
content (0.45 % weight) and low concentrations of heavy metals
such as nickel and vanadium, he said.
Other crude characteristics include an API gravity of 21.5°,
a total acid number of 4.4 mg KOH/g, and a low pour point of -27°C.
No waxing or asphaltene problems have been encountered.
The characteristics of Alba crude have certainly been a major
factor in shaping the different aspects of the development: from
its oil production wells to the design of equipment on the Alba
Northern platform where the crude is processed before being held
aboard the North Sea's first purpose-built floating storage
unit (FSU) ready for export by shuttle tanker.
Dave Dawson of Chevron spoke briefly about the Alba field. He explained that devel-opment complexities include relatively heavy oil (20° API), unconsolidated formation, exclusive use of horizontal producers, bottom water, water injection, complex completion procedures, scaling, difficult top of sand seismic resolution, electric submersible pumps (ESPs), and seismically unresolvable shales in the main sand body along the planned well paths.
Field development was originally approved with a phased approach.
The first phase consists of a minimum facilities platform -
Alba Northern - and a floating storage unit with a capacity
of 825,000 barrels. The crude is offloaded to a dedicated shuttle
tanker. First production was in January 1994.
The southern section of the reservoir will be developed with extended
reach wells from Alba Northern and possibly a bridge-linked support
platform and subsea wells depending on the outcome of studies
currently in progress. Dispensing with the need for a second major
platform has helped reduce development costs considerably.
The lack of pressure support in the reservoir has necessitated
water injec-tion from production start-up. 'Water-flooding
has worked well,' Dave noted. 'We have successfully
maintained reservoir pressure above the bubble point of 2300 psia
and inject-ivities of up to 70,000 barrels a day of water are
being achieved in some wells.'
Artificial lift techniques were also identified as essential from
the outset and it was decided to install ESPs in the initial completions.
However, they have not been installed in some of the more recent
wells due to high reservoir pressures, low water cuts and excess
well deliverability.
As was the case for Gryphon, Dave pointed out that the design
of the topsides process facilities was the key area impacted by
the heavy, viscous (20 cp at 70°C) nature of Alba crude.
The two first-stage separators, measuring an enormous 26m in length
and 4.3m in diameter, became the major consideration in setting
the size, weight, and consequently the cost of the topsides design.
Each separator spans the entire width of the platform's
processing deck.
The oil has to be heated to lower its viscosity and enhance the
separation process in what is one of the biggest heat transfer
operations in the North Sea. A third coalescer/degasser module
has recently been added to the Alba Northern platform, marking
the beginning of the phase two development and allowing oil production
to increase to 100,000 barrels a day.
Electrostatic coalescers further reduce the water content of the
crude to the low level required for export, while the oily sand
produced is cleaned thoroughly by passing it through innovative
ceramic hydrocyclones.
The Alba development presented a number of new challenges for
a North Sea project and valuable lessons have been learned for
the future. So, with hindsight, what might have been done differently?
Dave suggested a range of issues associated with the separation
process - for instance, increasing the heat at the first
stage, installing the separators in a series with interstage heating
rather than as separate trains, injecting demulsifier as far upstream
as possible to allow maximum 'break out' time, and
taking steps to minimise internal flow disturbances in the very
long separators.
Harding crude is a more recent entrant to the market, having come
on stream earlier this year. Adrian Pearce of BP explained
that the main Central and South pools were first discovered in
1988, with project sanction and development approval given by
the government in 1993.
Harding is another heavy North Sea crude ñ 19.5-21.0° API, viscosity of 5-10 centipoise, and total acid number of 2.8 mg KOH/g ñ and its early commercial viability was cast further in doubt by the shallow and complex nature of the reservoir. However, advances in extended reach and horizontal well technology led to a development proposal based on:
The reservoir quality of Harding is excellent by North Sea standards
- very homogenous with a porosity of 35 per cent and permeability
of up to ten Darcies. A total of 16 wells have been planned, nine
of which will be horizontal production wells. Two wells will be
water producers (Harding formation water is incompatible with
sea water) and the remaining five will be used for water and gas
injection to maintain pressure, minimise flaring and maximise
recovery. The horizontal sections in the first wells drilled were
positioned some 75 ft below the gas cap to maximise the early
production rate; later ones will be drilled shallower to improve
ultimate oil recovery.
Field life is expected to be some 20 years with peak oil production
of around 70,000 barrels per day. Associated gas will initially
be re-injected into the reservoir with exports not commencing
until oil production is in decline.
The facilities design on the platform allows for the high water
production expected later in field life. As with Gryphon and Alba,
the separators are large and a main challenge, according to Adrian,
is to heat the crude sufficiently to reduce its viscosity and
facilitate gas/oil separation.
Unlike many heavy crudes, Harding oil has no wax or asphaltene
problems and is also low in sulphur.
SPE London Section : Return to home page